Half Way There!

Construction of the Tallahassee Memorial Emergency Center - Northeast is half way completed! The walls and ceilings of all three floors are in process and the exterior framing and sheathing of the building is 99 percent completed. The west stairs have been completed, and the east stairs are 75 percent complete.

If you're in the area and have never had the luxury of seeing a concrete pour, there is one scheduled for the roof today! In preparation for the pour, the steel erection crews installed tube steel below the roof for support.



We can't wait until the outside of the building is completed and the inside work begins. Don't forget to check our "Watch Construction" page regularly for real-time construction photos of the emergency center!